THE CURRENT PROGRESS OF CONSTRUCTION WORKS

 

Hydraulic and electrical works inside the building

 

 

 

 

 

dav
Attic knee wall height about 145 cm
Wall works, partition walls inside the apartments
The final stage of works with the roof and ceilings.
Cleansing and impregnation of ceiling beams on wooden ceilings.
Ceiling above the basement, keramzyt, reinforcement and concrete screed.
Pouring the floor
 Further work on the roof
Timber foor truss mounted on the larger part of the roof.
  Wall plate located on the outer rims, the attic walls rims completed preparation for the construction of a larger part of the roof.
          Demolition of damaged parts of chimneys and damaged parts of external walls, making new chimneys and walls, making a wreath under the rafter around the attic, new walls on the residential part of the attic.
Installation of a wooden structure of the upper part of the roof.

 

 

 

 

 

Cover the roof, demolished, putting new walls under the new roof construction, pouring wreaths fastening the external walls of the building and as a basis for a new roof truss.

 

 

 

 

 

 

 

 

 

 

 

Strengthening and insulating the attic walls before mounting the roof truss.

 

 

The demolition of the roof started.

 

Current works consist in pouring the ceiling in the attic.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

At present, the works include construction of a wreath for a new ceiling. The works include demolition of old ceilings and removal of old plasters.

 

 